The second floor

Summer 2008 :

The workmen finish the roof, notably the part which overlooks the courtyard.








Spring 2008 :

A lorry equipped with an arm discharges the tonnes of concrete needed to lay a new slab over the whole of the second floor.







Autumn 2008 :

The restoration of the roof is begun again over the whole of the South wing, the timbers are strengthened, several beams are replaced by ones that look the same.








Autumn 2007 :

A huge building-operation begins, with the aim of creating 16 cells and 2 common-rooms in the 1000 m2 of the second floor.